AWD & LHD Ship Sustainment Facilities Project
The project is to enable the berthing of Landing Helicopter Deck (LHD) warships at Fleet Base East (FBE) Wharves 1 to 4 at Garden Island, Woolloomooloo. The...
Underground Investigation Services, Surveying, bore hole investigation, Pile trimming i.e. jack hammering or Quicutter debonding foam, Pile cap steel fixing, concreting, curing and thermal monitoring.
Avopiling extends services to organisations who are in need of specialty packages such as ground utility inspections, surveying, bore hole investigation, pile trimming using air hammers or debonding material using Quicutter, disposal of contaminated pile spoil material, pile cap steel fixing and concreting, curing and thermal monitoring.
The project is to enable the berthing of Landing Helicopter Deck (LHD) warships at Fleet Base East (FBE) Wharves 1 to 4 at Garden Island, Woolloomooloo. The project is in two stages, first is the AWD & LHD SPO/TLSF Building then the construction of 4No of Storm Bollards located within Wharves 1-4.
The works involved were excavating, bored piling, sheetpiling, pile trimming, blinding, steel fixing, formworking, concreting of pile caps including restoration of pavers in surrounding area of pile caps. Piling involves installation of 4No. 1350mmØ bored raked piles for each storm bollard pile caps with permanent casings ranging from 15 to 32 metres long and drill depths from 17 to 45 metres.
In June 2013, South East Queensland Water (SEQ Water) awarded Avopiling the contract that included a deep bored pile retention wall, permanent anchors, a deep capping beam and various ancillary civil work packages. The project was classified as a critical infrastructure project as an existing landslip that had been exacerbated by recent flooding was threatening the stability of two high pressure water mains that fed Ipswich via the treatment plant at Goodna. Avopiling acted as the Principle Contractor for the Project.
In order to safely set up the piling rig on top of the slip patch a detailed investigation was completed to test the stability of an existing road that would form part of the piling platform. Once the two rigs, cranes and polymer plant was established, the piling work ran from August until October 2013.
Despite the challenging ground conditions including a high water table and deep band of loose gravels, all 60No 1200 mmØ piles to depth of 30 meters were constructed with the use of a polymer/bentonite mixture to act as bore support which in turn facilitated a deeper rock socket due to a possible lack of adhesion.
A heavily reinforced capping beam structure, 2m deep by 2m wide cast in situ member was built and shaped in a chamfered profile on one edge to house the future anchor plate. The construction of the beam was carried out in house with the assistance of formwork subcontractors. After completion of approximately half of the beam we mobilised a ground anchor machine and conducted three trial anchors to verify the anchor design. With the tests complete two percussive rigs were utilised to drill 34 deep ground anchors. Each anchor consisted of 12 strands of 15.2mm diameter high tensile (super grade) strands that extended into the competent siltstone rock 34m into the ground. Each anchor was grouted and locked off at a working load of 3000kN.
The project is to enable the berthing of Landing Helicopter Deck (LHD) warships at Fleet Base East (FBE) Wharves 1 to 4 at Garden Island, Woolloomooloo. The...
In June 2013, South East Queensland Water (SEQ Water) awarded Avopiling the contract that included a deep bored pile retention wall, permanent anchors, a deep capping...